| KEEPING INNOVATION ALIVE - TOUCHWOOD The following photo's depict the actual time frame for erecting prefabricated walls for a typical 90m2 Touchwood home.

8:00am - Touchwood walls arrive on site 9:00am - Crane arrives and the first 2 walls and are placed near floor for easy access. are located and fixed into possition.

10:00am - Walls continue to fall into place 11:00am - The last of the walls are dropped and people are flocking to see what all the into place. the fuss is about.

12:00Noon - All Touchwood walls are up and the crane driver has departed. A number of people have stayed to watch our progress and learn about the new system.
 
Finished Product
|